If your power trips when the oven and washing machine run together, you most likely have too little contracted power. But increasing it is not always the answer: sometimes spreading usage out is enough, and sometimes the problem is in the installation.

First: what is tripping?

Before asking for more power, identify which device is switching off:

  • ICP / power limiter (or a cut from the smart meter): you have exceeded your contracted power. Increasing it does help here.
  • A specific circuit breaker (PIA): that circuit is overloaded. More contracted power will not fix it — the circuit needs checking.
  • RCD (diferencial): this is an earth leakage, not excess consumption. See why your RCD keeps tripping.

How much power do you need?

Add up the appliances you use at the same time, not everything in the house. As a reference:

Appliance Approximate power
Oven 2 – 3 kW
Induction hob 3 – 7 kW (depending on zones in use)
Washing machine or dishwasher (heating) 2 – 2.5 kW
Electric water heater 1.5 – 2 kW
Air conditioning / heat pump 1 – 3 kW
EV charger 3.7 – 7.4 kW

A flat with an electric kitchen usually manages with 4.6 – 5.75 kW. With a heat pump or an EV, 6.9 – 9.2 kW is common — or you can manage loads to avoid it.

Remember: you pay for power every month whether you use it or not. Over-contracting is money wasted.

Steps to increase your power

  1. Check your certificate (boletín). It states your installation’s maximum admissible power. If the new power is below it, you usually just ask your retailer for the change.
  2. If you exceed it, upgrade and certify. A licensed installer checks the supply line, consumer unit and protection, makes the necessary changes and issues a new certificate.
  3. Request to your retailer. With the certificate (if needed), you request the power change. The retailer passes it to the distributor for your area.
  4. Change applied. With a smart meter, it is usually done remotely.

How much does it cost?

There are two parts:

  • Regulated distributor fees: charged on your next bill per kW added (access and, where applicable, extension rights), plus a small connection fee. As a guide, about €20 – €40 per kW added plus VAT.
  • Installation work, only if an upgrade is needed: from adjusting protection to replacing the supply line. This is where prices vary most.

Alternatives to increasing power

  • Load manager: for EVs or heat pumps, a device that reduces the load when the house is using a lot, avoiding a higher contract.
  • Scheduling: run the dishwasher, washing machine and water heater at different times.
  • Dual power: contract extra power only in off-peak hours.

At COMA Electrics we calculate the power you actually need, upgrade the installation if required and guide you through the process. See our power increase service or get a quote.

Frequently asked questions

How long does a power change take?

With a smart meter, if no new certificate is needed, the distributor usually makes the change remotely within a few days. If the installation needs work, that and the certificate come first.

Can I lower my power later?

Yes, but the distributor may not accept another change for 12 months. That is why it pays to calculate your power properly before asking.

Can I contract more power during off-peak hours?

Yes. Since 2021 you can contract two power levels in Spain, one for peak and one for off-peak hours. Useful if you charge an EV overnight.